Capital Projects List
Capital Projects
Zoology Building Refurbishment
| Description | The works are the final phase of the Zoology Building with refurbishment of the 4th floor along with some ancillary works. This phase comprises the upgrading of Laboratory and Office space, escape routes and fire protection and improvement of disabled facilities. |
|---|---|
| Programme | Start Spring 2007 Completion Winter 2008 |
| Budget | £2,750,000 |
| Design Team | Architect: George Watt & Stewart Structural & Civil Engineers: Cameron & Ross Mechanical & Electrical Services: Hulley & Kirkwood Quantity Surveyor: Baxter Dunn & Gray CDM Co-ordinator: George Watt & Stewart |
| Main Contractor | Burns Construction (Aberdeen) Ltd |
| Project Manager | John McManus Tel No: 01224 273335 E-mail: j.e.mcmanus@abdn.ac.uk |